Plan satellite lifecycle

Table of Contents

Most student satellite projects aim to start and complete satellite design and launch within two years. To achieve this requires meticulate planning and forsight.

  • Table of Contents

Make Satellite Schedule

Breaking down the schedule of a CubeSat project involves organizing the work into phases, milestones, and activities to ensure timely delivery. Here’s a typical schedule breakdown:

1. Mission Concept and Feasibility (3-6 months)

Key Activities:

  • Define mission objectives (e.g., Earth observation, technology demonstration).
  • Identify stakeholders and users.
  • Conduct a feasibility study (technical, financial, and operational).
  • Preliminary budget and timeline estimation.
  • Review: Concept Review (CoR).

2. System Design and Development (6-12 months)

Key Activities:

  • Preliminary Design:
    • Develop system architecture.
    • Perform trade-off analyses for subsystems (ADCS, EPS, Payload, etc.).
    • Create a mission operations plan.
    • Conduct risk analysis and mitigation planning.
    • Review: Preliminary Design Review (PDR).
  • Detailed Design:
    • Define subsystem-level specifications.
    • Begin component selection and procurement.
    • Develop simulation and analysis tools.
    • Conduct environmental and mechanical analyses.
    • Review: Critical Design Review (CDR).

3. Assembly, Integration, and Testing (AIT) (6-9 months)

Key Activities:

  • Assemble subsystem prototypes for testing.
  • Develop Ground Support Equipment (GSE).
  • Integrate CubeSat hardware components.
  • Develop and validate software (flight and ground).
  • Perform environmental tests:
    • Thermal-vacuum testing.
    • Vibration testing.
    • Radiation testing (if applicable).
    • Electromagnetic compatibility (EMC) tests.
  • Functional testing of the integrated system.
  • Review: Test Readiness Review (TRR).

4. Launch Integration and Operations Readiness (3-6 months)

Key Activities:

  • Coordinate with the launch provider:
    • Payload interface definition.
    • CubeSat delivery to the integration facility.
  • Conduct final functional tests.
  • Perform pre-launch verification (battery charging, software updates).
  • Train the operations team.
  • Develop and test the ground station.
  • Review: Flight Readiness Review (FRR).

5. Launch and Early Orbit Phase (LEOP) (1-3 months)

Key Activities:

  • Launch vehicle integration and deployment.
  • Initial contact with the satellite.
  • Perform health checks and commissioning tests.
  • Activate primary payload and subsystems.

6. Nominal Operations Phase (6-24 months)

Key Activities:

  • Conduct mission operations:
    • Execute planned maneuvers.
    • Collect and analyze data from the payload.
  • Monitor CubeSat health (telemetry analysis).
  • Troubleshoot and resolve anomalies.
  • Publish mission results and share data (if applicable).

7. End-of-Life and Decommissioning (1-3 months)

Key Activities:

  • Execute deorbiting maneuvers or passive end-of-life measures.
  • Assess lessons learned for future missions.
  • Publish a mission summary report.

Example CubeSat Schedule

Gantt Chart Breakdown:

Phase Start Duration Milestone
Mission Planning Month 1 3 months Concept Review (CoR)
System Design Month 4 6 months Preliminary Design Review
Subsystem Development Month 10 9 months Critical Design Review
Integration & Testing Month 19 6 months Test Readiness Review (TRR)
Launch & Commissioning Month 25 3 months Launch Readiness Review
Operations Phase Month 28 1-2 years Final Mission Report

Notes:

  • Overlaps: Some phases overlap, especially design, procurement, and testing.
  • Customization: The schedule depends on mission complexity, budget, and team size.
  • Milestone Reviews: Regular reviews ensure progress aligns with goals.

In project management, schedules are used to manage and track time, resources, and deliverables. Different types of schedules serve distinct purposes, and in a CubeSat project, you might encounter or use several of these. Here’s a breakdown:


Types of Schedules

1. Master Schedule

  • Purpose:
    Provides a high-level overview of the entire project timeline.
  • Key Features:
    • Summarizes all phases (concept, design, testing, etc.).
    • Used for stakeholder communication and major milestone tracking.
  • Example Milestones in a CubeSat Project:
    • Preliminary Design Review (PDR).
    • Critical Design Review (CDR).
    • Launch Readiness.

2. Detailed Schedule

  • Purpose:
    Breaks down each phase into specific tasks and sub-tasks.
  • Key Features:
    • Includes task dependencies and durations.
    • Assigns resources to tasks.
    • Often visualized using Gantt charts.
  • Use Case:
    Managing subsystem developments like ADCS (Attitude Determination and Control System).

3. Critical Path Schedule

  • Purpose:
    Focuses on the sequence of tasks that determine the project’s overall duration.
  • Key Features:
    • Identifies tasks that, if delayed, will delay the entire project.
    • Used to optimize resource allocation and reduce delays.
  • Example in CubeSat Projects:
    A delay in testing solar panels might postpone integration and launch readiness.

4. Milestone Schedule

  • Purpose:
    Tracks key deliverables and deadlines without detailed task lists.
  • Key Features:
    • Focuses only on milestones (e.g., design reviews, component deliveries).
    • Easier for reporting to high-level stakeholders.
  • Example:
    • Concept Approval: Month 3.
    • Payload Delivery: Month 12.

5. Resource Schedule

  • Purpose:
    Ensures the availability and allocation of human, financial, and material resources.
  • Key Features:
    • Tracks resource usage over time.
    • Highlights potential resource conflicts.
  • Use Case:
    Managing lab access for testing or ensuring team availability during key phases.

6. Baseline Schedule

  • Purpose:
    Serves as the original project timeline for tracking deviations.
  • Key Features:
    • Acts as a reference point for progress monitoring.
    • Helps measure schedule performance (planned vs. actual).
  • Use Case:
    Comparing planned satellite assembly timelines with actual progress.

7. Agile or Iterative Schedule

  • Purpose:
    Supports flexible development cycles for software-heavy projects.
  • Key Features:
    • Tasks grouped into short sprints or iterations.
    • Continuous adjustments based on progress and feedback.
  • Use Case:
    Developing and testing CubeSat flight software in iterations.

8. Integrated Schedule

  • Purpose:
    Combines schedules across different teams or subsystems.
  • Key Features:
    • Aligns efforts across hardware, software, and testing teams.
    • Manages dependencies between teams (e.g., payload delivery for integration).
  • Example:
    Aligning ADCS development with power subsystem testing.

9. Rolling Wave Schedule

  • Purpose:
    Plans in detail for near-term activities while keeping long-term phases high-level.
  • Key Features:
    • Focuses on immediate tasks while refining future phases as more information becomes available.
  • Use Case:
    Planning detailed integration steps while keeping launch preparations flexible.

10. Contingency Schedule

  • Purpose:
    Accounts for potential delays or risks.
  • Key Features:
    • Includes buffer time for critical tasks.
    • Identifies alternative plans for high-risk activities.
  • Use Case:
    Adding buffer weeks for component delivery delays.

Visual Tools for Scheduling

  • Gantt Charts:
    Good for detailed and master schedules.
  • PERT Charts:
    Useful for critical path and task dependencies.
  • Kanban Boards:
    Ideal for Agile schedules.
  • Dashboards:
    Combine multiple schedules into one interactive view.

Organise Meetings Back to guide