Plan satellite lifecycle
Table of Contents
- Make Satellite Schedule
- 1. Mission Concept and Feasibility (3-6 months)
- 2. System Design and Development (6-12 months)
- 3. Assembly, Integration, and Testing (AIT) (6-9 months)
- 4. Launch Integration and Operations Readiness (3-6 months)
- 5. Launch and Early Orbit Phase (LEOP) (1-3 months)
- 6. Nominal Operations Phase (6-24 months)
- 7. End-of-Life and Decommissioning (1-3 months)
- Types of Schedules
Most student satellite projects aim to start and complete satellite design and launch within two years. To achieve this requires meticulate planning and forsight.
- Table of Contents
Make Satellite Schedule
Breaking down the schedule of a CubeSat project involves organizing the work into phases, milestones, and activities to ensure timely delivery. Here’s a typical schedule breakdown:
1. Mission Concept and Feasibility (3-6 months)
Key Activities:
- Define mission objectives (e.g., Earth observation, technology demonstration).
- Identify stakeholders and users.
- Conduct a feasibility study (technical, financial, and operational).
- Preliminary budget and timeline estimation.
- Review: Concept Review (CoR).
2. System Design and Development (6-12 months)
Key Activities:
- Preliminary Design:
- Develop system architecture.
- Perform trade-off analyses for subsystems (ADCS, EPS, Payload, etc.).
- Create a mission operations plan.
- Conduct risk analysis and mitigation planning.
- Review: Preliminary Design Review (PDR).
- Detailed Design:
- Define subsystem-level specifications.
- Begin component selection and procurement.
- Develop simulation and analysis tools.
- Conduct environmental and mechanical analyses.
- Review: Critical Design Review (CDR).
3. Assembly, Integration, and Testing (AIT) (6-9 months)
Key Activities:
- Assemble subsystem prototypes for testing.
- Develop Ground Support Equipment (GSE).
- Integrate CubeSat hardware components.
- Develop and validate software (flight and ground).
- Perform environmental tests:
- Thermal-vacuum testing.
- Vibration testing.
- Radiation testing (if applicable).
- Electromagnetic compatibility (EMC) tests.
- Functional testing of the integrated system.
- Review: Test Readiness Review (TRR).
4. Launch Integration and Operations Readiness (3-6 months)
Key Activities:
- Coordinate with the launch provider:
- Payload interface definition.
- CubeSat delivery to the integration facility.
- Conduct final functional tests.
- Perform pre-launch verification (battery charging, software updates).
- Train the operations team.
- Develop and test the ground station.
- Review: Flight Readiness Review (FRR).
5. Launch and Early Orbit Phase (LEOP) (1-3 months)
Key Activities:
- Launch vehicle integration and deployment.
- Initial contact with the satellite.
- Perform health checks and commissioning tests.
- Activate primary payload and subsystems.
6. Nominal Operations Phase (6-24 months)
Key Activities:
- Conduct mission operations:
- Execute planned maneuvers.
- Collect and analyze data from the payload.
- Monitor CubeSat health (telemetry analysis).
- Troubleshoot and resolve anomalies.
- Publish mission results and share data (if applicable).
7. End-of-Life and Decommissioning (1-3 months)
Key Activities:
- Execute deorbiting maneuvers or passive end-of-life measures.
- Assess lessons learned for future missions.
- Publish a mission summary report.
Example CubeSat Schedule
Gantt Chart Breakdown:
Phase | Start | Duration | Milestone |
---|---|---|---|
Mission Planning | Month 1 | 3 months | Concept Review (CoR) |
System Design | Month 4 | 6 months | Preliminary Design Review |
Subsystem Development | Month 10 | 9 months | Critical Design Review |
Integration & Testing | Month 19 | 6 months | Test Readiness Review (TRR) |
Launch & Commissioning | Month 25 | 3 months | Launch Readiness Review |
Operations Phase | Month 28 | 1-2 years | Final Mission Report |
Notes:
- Overlaps: Some phases overlap, especially design, procurement, and testing.
- Customization: The schedule depends on mission complexity, budget, and team size.
- Milestone Reviews: Regular reviews ensure progress aligns with goals.
In project management, schedules are used to manage and track time, resources, and deliverables. Different types of schedules serve distinct purposes, and in a CubeSat project, you might encounter or use several of these. Here’s a breakdown:
Types of Schedules
1. Master Schedule
- Purpose:
Provides a high-level overview of the entire project timeline. - Key Features:
- Summarizes all phases (concept, design, testing, etc.).
- Used for stakeholder communication and major milestone tracking.
- Example Milestones in a CubeSat Project:
- Preliminary Design Review (PDR).
- Critical Design Review (CDR).
- Launch Readiness.
2. Detailed Schedule
- Purpose:
Breaks down each phase into specific tasks and sub-tasks. - Key Features:
- Includes task dependencies and durations.
- Assigns resources to tasks.
- Often visualized using Gantt charts.
- Use Case:
Managing subsystem developments like ADCS (Attitude Determination and Control System).
3. Critical Path Schedule
- Purpose:
Focuses on the sequence of tasks that determine the project’s overall duration. - Key Features:
- Identifies tasks that, if delayed, will delay the entire project.
- Used to optimize resource allocation and reduce delays.
- Example in CubeSat Projects:
A delay in testing solar panels might postpone integration and launch readiness.
4. Milestone Schedule
- Purpose:
Tracks key deliverables and deadlines without detailed task lists. - Key Features:
- Focuses only on milestones (e.g., design reviews, component deliveries).
- Easier for reporting to high-level stakeholders.
- Example:
- Concept Approval: Month 3.
- Payload Delivery: Month 12.
5. Resource Schedule
- Purpose:
Ensures the availability and allocation of human, financial, and material resources. - Key Features:
- Tracks resource usage over time.
- Highlights potential resource conflicts.
- Use Case:
Managing lab access for testing or ensuring team availability during key phases.
6. Baseline Schedule
- Purpose:
Serves as the original project timeline for tracking deviations. - Key Features:
- Acts as a reference point for progress monitoring.
- Helps measure schedule performance (planned vs. actual).
- Use Case:
Comparing planned satellite assembly timelines with actual progress.
7. Agile or Iterative Schedule
- Purpose:
Supports flexible development cycles for software-heavy projects. - Key Features:
- Tasks grouped into short sprints or iterations.
- Continuous adjustments based on progress and feedback.
- Use Case:
Developing and testing CubeSat flight software in iterations.
8. Integrated Schedule
- Purpose:
Combines schedules across different teams or subsystems. - Key Features:
- Aligns efforts across hardware, software, and testing teams.
- Manages dependencies between teams (e.g., payload delivery for integration).
- Example:
Aligning ADCS development with power subsystem testing.
9. Rolling Wave Schedule
- Purpose:
Plans in detail for near-term activities while keeping long-term phases high-level. - Key Features:
- Focuses on immediate tasks while refining future phases as more information becomes available.
- Use Case:
Planning detailed integration steps while keeping launch preparations flexible.
10. Contingency Schedule
- Purpose:
Accounts for potential delays or risks. - Key Features:
- Includes buffer time for critical tasks.
- Identifies alternative plans for high-risk activities.
- Use Case:
Adding buffer weeks for component delivery delays.
Visual Tools for Scheduling
- Gantt Charts:
Good for detailed and master schedules. - PERT Charts:
Useful for critical path and task dependencies. - Kanban Boards:
Ideal for Agile schedules. - Dashboards:
Combine multiple schedules into one interactive view.